[ad_1]
DNV ensured the completeness and correct execution of necessary Web site Execution Take a look at (SAT) actions, an necessary milestone on the way in which to launch the 285 megawatt hour (MWh) ESS into industrial operation, marking the completion of the plant qualification course of.
DNV’s position within the ESS undertaking lined witnessing the mandated exams, processing the uncooked information, and approving the ultimate commissioning reviews from two completely different unique tools producers, Huawei and Envision.
The undertaking went on-line as deliberate in December 2022, as scheduled by Sembcorp. Commissioning the undertaking took solely six months in comparison with the trade common of 15 to 18 months for comparable capability installations. “Regardless of the very tight timeline set, adhering to the schedule was vital on this undertaking. This required us to undertake an agile manner of working that concerned an everyday overview and strict adherence to priorities,” stated Dr. George Garabandic, DNV undertaking supervisor and Vitality Storage Methods Lead, APAC.
“The 285MWh Sembcorp ESS on Jurong Island, the most important in Southeast Asia, was commissioned in six months, making it the quickest deployment of its measurement on the planet. These milestones had been solely made attainable by the shut partnership between Sembcorp and DNV, who offered their power storage trade experience and impartial validation companies in help of the record-setting deployment,” stated Chua Kia, Head, Challenge Administration Workplace, Singapore & Southeast Asia, Sembcorp Industries.
Brice le Gallo, DNV’s Vice President and Regional Director, Vitality Methods for Asia Pacific, stated: “We’re delighted to have been trusted with this work on the most important utility-scale ESS in Southeast Asia. As demonstrated by this undertaking that may cowl the wants of round 24,000 households, power storage is a central component supporting the deployment of solar energy – one of many 4 ‘switches’ recognized for Singapore’s power transition. We now have performed a key position in Sembcorp’s power storage system on Jurong Island and are wanting ahead to being concerned with many such initiatives sooner or later.”